CONSTRUCTION WORK OF SELÇUK - ORTAKLAR - AYDIN ROAD KM:0+000 - 46+400 SECTION

GENERAL DIRECTORATE OF HIGHWAYS

CONTRACT DATE: 14.11.2013

The existing 46 km long state road between İzmir's Selçuk district and Aydın will be widened and 2x2 double and hot mix asphalt coating will be made. Within the scope of the project, 2,500,000 m³ soil movement, 950,000 tons of PMAT and PMT, 1,000,000 m² asphalt coating will be carried out. 